Handle & Price Change Orders in Construction Projects

April 25, 2025
9 min read
Table of Contents
handle-price-construction-change-orders

Mastering Construction Change Order Pricing in Commercial Projects

For commercial building construction businesses, change orders are an inevitable part of the project lifecycle. While often necessary to accommodate unforeseen conditions or evolving client needs, they can significantly impact project timelines, budgets, and most critically, your profitability.

Poorly managed or incorrectly priced change orders are a leading cause of disputes and financial losses in construction. This guide provides practical strategies for handling and pricing construction change orders effectively in 2025 and beyond, helping you protect your margins and maintain strong client relationships.

Understanding the Nature and Impact of Construction Change Orders

A construction change order is formally defined as an amendment to the original construction contract that alters the scope of work, cost, or schedule.

They can arise from various sources:

  • Client Requests: Changes in design preferences, materials, or scope after the contract is signed.
  • Unforeseen Conditions: Discovering unexpected site conditions (e.g., soil issues, hidden obstructions) that require different approaches.
  • Design Errors or Omissions: Issues identified in the architectural or engineering plans during construction.
  • Regulatory Changes: New codes or requirements emerging after the project begins.
  • Delays by Others: Impacts from other trades, client-furnished items, or external factors.

Regardless of the cause, each change order represents a potential disruption. Efficiently managing the communication, documentation, and especially the construction change order pricing is paramount to converting these potential issues into controlled project adjustments.

Establishing a Robust Change Order Process

A clear, standardized process is the foundation of effective change order management. This process should be outlined in your initial contract and consistently followed for every potential change.

Key steps include:

  1. Identification and Notification: The moment a potential change is identified (by you, the client, or a subcontractor), it must be formally documented.
  2. Assessment: Evaluate the impact on scope, schedule, and cost. This requires input from relevant team members, subcontractors, and suppliers.
  3. Pricing and Proposal: Based on the assessment, calculate the cost and propose the change order price to the client. This is where accurate construction change order pricing is critical.
  4. Client Review and Approval: The client reviews the proposed change order, including the scope description, price, and schedule impact.
  5. Authorization: The change order must be formally approved and signed by the client before work begins on the altered scope. Never proceed with change order work based on verbal approval alone.
  6. Execution and Documentation: Implement the change and maintain detailed records of all related costs, labor hours, materials, and communications.

Calculating the True Cost of a Change Order

Accurate cost calculation is the bedrock of profitable construction change order pricing. Don’t just estimate; calculate based on actual anticipated expenses.

Break down the costs systematically:

  • Direct Labor: Hours x burdened labor rate (includes wages, payroll taxes, insurance, benefits). Be specific about which team members are involved and for how long.
    • Example: Adding a structural beam might require an extra 40 hours of a foreman’s time ($65/hour burdened rate) = $2,600.
  • Materials: Itemized list of all required materials, quantities, and current supplier costs. Include delivery fees and potential waste.
    • Example: Additional concrete mix and rebar for a footing modification = $1,850.
  • Subcontractors: Obtain formal quotes from any subcontractors whose work is affected by the change. Include their markup.
    • Example: Rerouting plumbing lines requires a plumbing sub-quote = $3,500.
  • Equipment: Costs for any additional equipment needed or extended use of existing equipment.
    • Example: Rental of a small excavator for an extra day = $450.
  • Indirect Costs: Don’t forget costs like project management time, supervision, additional permits, site-specific overhead directly attributable to the change.
    • Example: Extra project manager time, revised drawings, site administration = $1,100.

Effective Pricing Strategies for Construction Change Orders

Once you have the total cost, you need to apply your markup to arrive at the final construction change order pricing for the client. Common methods include:

  1. Cost-Plus Markup: This is perhaps the most common for change orders. You add a predetermined percentage markup to the total calculated cost. The markup needs to cover your overhead costs (the ones not directly tied to this specific change) and your desired profit margin.
    • Formula: Total Cost + (Total Cost x Markup Percentage) = Change Order Price
    • Example: If the total cost is $9,500 and your standard change order markup is 20%, the price is $9,500 + ($9,500 x 0.20) = $11,400.
  2. Fixed Fee: Less common for true change orders resulting from unforeseen issues, but applicable if the change is very clearly defined and carries little risk (e.g., adding a specific, standard fixture). You agree on a fixed price upfront.
  3. Time & Materials (T&M): Sometimes used for ill-defined or high-risk change orders, especially early in a project. You bill for actual hours worked (at agreed-upon rates) plus the cost of materials (often with a percentage handling fee). This shifts risk to the client but requires meticulous tracking and can feel less predictable for them.

Key Considerations for Your Markup:

  • Overhead Recovery: Does your markup adequately cover your general business overhead (office rent, utilities, insurance, etc.)?
  • Profit Margin: What profit do you need to make on this work?
  • Risk: Higher risk changes (uncertain scope, complex execution) warrant a higher markup.
  • Complexity: More complex changes requiring specialized knowledge or coordination justify a higher rate.
  • Schedule Impact: Changes causing significant disruption or requiring overtime should factor into the pricing.

Your contract should clearly define how change orders will be priced (e.g., Cost-Plus with X% markup on labor, Y% on materials, Z% on subcontractors). Consistency is key.

Presenting Change Order Pricing to Clients

How you present the construction change order pricing significantly impacts client acceptance and satisfaction. Avoid simply handing over a number.

A professional change order proposal should include:

  • Clear Title: “Change Order # [Number]”
  • Reference: To the original contract and affected area/task.
  • Detailed Description: Precisely what work is being added, removed, or changed.
  • Reason for Change: Explain why the change is necessary or requested.
  • Impact on Schedule: Clearly state how this change affects the project timeline.
  • Cost Breakdown: Provide enough detail so the client understands where the costs come from (labor hours, materials list, subcontractor quotes). You don’t have to reveal your internal markup percentage, but show the underlying costs.
  • Total Price: The final, clear price for the change.
  • Terms: Payment terms specific to the change order.
  • Approval Signature Line: For client authorization.

Presenting this information professionally and transparently builds trust. For service businesses looking to provide a modern, interactive way for clients to review and approve pricing, especially with configurable options or tiered change impacts, a tool like PricingLink (https://pricinglink.com) can be highly effective. While not a full proposal or e-signature tool (for that, consider solutions like PandaDoc (https://www.pandadoc.com) or Proposify (https://www.proposify.com)), PricingLink excels at presenting the pricing component interactively. You could potentially model common change order scenarios or add-ons within PricingLink, allowing clients to select and immediately see the price impact, streamlining the approval stage for certain types of changes.

Thorough documentation is your best protection in construction, especially with change orders.

  • Written Everything: All change order requests, assessments, pricing proposals, and approvals must be in writing.
  • Formal Change Order Form: Use a standardized form for all change orders.
  • Detailed Tracking: Maintain meticulous records of labor hours, materials used, and communications related to each change order.
  • Impact Logs: Keep logs detailing delays or impacts caused by pending or approved change orders.
  • Contract Clarity: Ensure your initial contract has a clear, enforceable change order clause outlining the process, pricing method, and timelines for approval.

Ignoring the formal process or failing to document meticulously can make it impossible to recover costs or defend yourself against claims related to change orders. Integrating project management software like Procore (https://www.procore.com) or Buildertrend (https://www.buildertrend.com) can help standardize documentation and tracking for both original scope and change orders, providing a central repository for project information.

Conclusion

  • Standardize Your Process: Implement a formal, written change order procedure and follow it rigorously.
  • Calculate Costs Accurately: Base your construction change order pricing on detailed, line-item cost breakdowns.
  • Price for Profit and Risk: Use a markup that covers your overhead, ensures profitability, and accounts for the complexity and risk of the specific change.
  • Present Transparently: Provide clients with clear, detailed change order proposals explaining the scope, schedule impact, and cost.
  • Document Everything: Maintain meticulous records of all change order communications, costs, and approvals.

Mastering construction change order pricing and management isn’t just about protecting your bottom line; it’s about maintaining trust and professionalism. By implementing clear processes, calculating costs accurately, pricing strategically, and communicating transparently, you can navigate change orders successfully, ensuring your projects remain profitable and your client relationships stay strong. Adopting modern tools for pricing presentation, like PricingLink (https://pricinglink.com), or comprehensive project management, like Procore or Buildertrend, can significantly enhance your capability to handle these critical project adjustments effectively.